Case Study: Implementing CargoON at Centrum Pali
Long loading wait times are a major challenge not only for drivers but also for warehouse managers in manufacturing companies. This issue is even more pronounced when large products are waiting to be loaded. For companies in the construction and building materials industries, where products can weigh tons, optimizing processes appears to be the only way to reduce queues and improve workflow efficiency.
Centrum Pali, a leading manufacturer of prefabricated reinforced concrete piles, faced this challenge and decided to take steps to significantly improve efficiency. The implementation of the CargoON platform, along with the Dock Scheduler module, proved to be a true game-changer, the details of which we present in our latest case study.
The Weight of the Challenge – Literally and Figuratively
As part of the international Per Aarsleff Holding A/S group, Centrum Pali manages large-scale transport operations daily. Each truck carrying foundation piles transports loads up to 57 linear meters in length and weighing up to 24 tons. On average, 60 fully loaded trucks depart from the company’s warehouses daily, putting enormous pressure on the entire logistics infrastructure.
Race Against Time
Before implementing the CargoON platform, Centrum Pali faced challenges common to many companies in the construction industry: long queues of trucks, extended loading wait times, and resulting dissatisfaction among drivers and carriers. The wait time for loading reached up to five hours, negatively impacting the efficiency of the entire process.
The implementation of Dock Scheduler in 2021 allowed for digitalizing these processes, resulting in impressive outcomes. Currently, the wait time has been significantly reduced to as little as 20 minutes. Furthermore, organizing transports more effectively has enabled better use of human resources—employees who were previously occupied with coordinating loads can now be assigned to other warehouse tasks, greatly boosting overall operational efficiency.
What Has the Transformation Brought?
One of the key insights from implementing Dock Scheduler was realizing that digitalization is not just a tool for optimization but also a driver for growth. Introducing Dock Scheduler allowed Centrum Pali to achieve impressive results:
- Reduced loading wait time from five hours to as little as 20 minutes
- Optimized warehouse and loading processes
- Lowered operational costs and increased efficiency
Want to learn more about this implementation and see it in action? We invite you to watch our video case study, where we walk you through how CargoON’s solutions transformed logistics at Centrum Pali step by step.